Pre-Excavation Planning Checklist: Before the First Bucket

Most excavation emergencies are planning failures. Run through this list before mobilizing so the protective system, utilities, access and rescue plan are settled before anyone digs.

  • Print or check off on screen
  • Nothing is saved
On this page
  1. Utilities and site
  2. Soil and water
  3. Protective systems
  4. Access, equipment and traffic
  5. Permits, rescue and training
  6. FAQ
Project / location
Planned start date
Max depth / width
Competent person
811 ticket number(s)
Prepared by

Use this checklist during job planning and again the day before excavation starts. It pairs with the excavation safety plan outline. Nothing you check is saved.

Utilities and site

Soil and water

Protective systems

Access, equipment and traffic

Permits, rescue and training

Sources and official references

Last reviewed: October 25, 2026 · Free general education based on OSHA 29 CFR 1926 Subpart P. It does not replace the site-specific training and competent person your employer must provide, and it does not issue a certificate. Nothing you enter on this page is saved or sent.

FAQ

Frequently asked questions

Locate utilities through 811 and private locators, evaluate soil, water and atmosphere, select and obtain the protective system and its tabulated data, plan access, spoil, equipment and traffic, obtain permits, plan emergency response, designate the competent person and brief the crew.

It depends on your state. Two to three full working days before excavation is common, but each state's one-call law sets its own notice period and ticket life.