Vacuum Excavation and Potholing: How to Expose Utilities Safely

Paint on the ground shows roughly where a line is. Potholing shows exactly where it is. Here is how vacuum excavation works and how to use it to dig safely near utilities.

  • 7 min read
  • Updated October 25, 2026
On this page
  1. Hydro vs. air vacuum excavation
  2. When to pothole
  3. Doing it right
  4. Why it pays
  5. FAQ

Potholing (also called daylighting or test holing) means digging a small hole to expose an underground utility and confirm its exact location, depth and direction before excavating near it. Today most potholing is done by vacuum excavation, a "soft dig" method that loosens soil with water or air and vacuums it into a truck.

Hydro vs. air vacuum excavation

MethodHow it worksProsCons
Hydro excavationPressurized water cuts the soil; the slurry is vacuumed into a debris tankFast in most soils, including clay and frozen groundProduces slurry to dispose of; wet spoil can't be reused as backfill right away
Air excavationCompressed air loosens soil; dry spoil is vacuumed upSpoil can be reused as backfill; no water neededSlower in hard clay; dust

Both are far less likely to damage a line than a bucket, though operators must still follow pressure and nozzle-distance limits to protect coatings and cables.

When to pothole

  • Inside the tolerance zone around marked lines, typically 18 to 24 inches on each side, set by state law.
  • Before boring or directional drilling across or near existing lines.
  • Where marks are unclear, conflicting or missing, or records are old.
  • At crossings where your excavation will pass over or under a line.
  • Before driving piles, posts or anchors near utilities.

Doing it right

  1. Confirm the 811 ticket is current and all owners have responded. See utility marking colors.
  2. Center the pothole on the mark and dig in small, controlled passes.
  3. When the line appears, expose enough to confirm direction, size and material.
  4. Record the location (station, offset, GPS), depth to top, size, material and owner, and photograph it.
  5. Protect and support the exposed line while it's open. OSHA requires underground installations to be protected, supported or removed as needed while an excavation is open (1926.651(b)(4)).
  6. Backfill per the owner's and agency's requirements, and restore the surface.

Why it pays

Utility strikes cause injuries, outages, fines and delays. A few potholes at crossings and inside tolerance zones cost far less than repairing a gas or fiber line.

Sources and official references

Last reviewed: October 25, 2026 · Free general education based on OSHA 29 CFR 1926 Subpart P. It does not replace the site-specific training and competent person your employer must provide, and it does not issue a certificate. Nothing you enter on this page is saved or sent.

FAQ

Frequently asked questions

Potholing is digging a small test hole, usually by vacuum excavation, to expose an underground utility and verify its exact location, depth and direction before excavating or boring nearby.

Hydro excavation uses pressurized water to loosen soil and vacuums up the slurry; it's fast in most soils. Air excavation uses compressed air and produces dry spoil that can be reused as backfill, but it's slower in hard clay.

State damage prevention laws generally require non-mechanical methods, such as hand digging or vacuum excavation, inside the tolerance zone around marked utilities. Check your state's one-call law.